Work through the same five-step method used in Philippine PV installer training β load analysis, panel sizing, inverter sizing, battery bank, and charge controller β for off-grid, on-grid, or hybrid systems.
System Settings
Philippines average is ~4β4.5 PSH (lower in rainy season / Luzon north, higher in Mindanao). Adjust to your site's solar resource data.
Higher bus voltage = lower current = smaller conductors, per PEC ampacity rules.
Covers wiring, temperature, dust, and inverter conversion losses β consistent with PEC's continuous-duty margin (conductors/OCPD sized β₯125% of load).
Roof / Site Dimensions
Checks whether the physical roof can actually fit the number of panels each mode recommends β not just the electrical sizing.
Clear pathway kept along ridges, hips, and eaves for fire access and maintenance β ~0.9m (3 ft) is a common minimum per fire code and TESDA rooftop-mounting practice.
of β mΒ² total roof area
System Wiring Diagram β Single Line
PV β charge controller β battery bank β inverter β main distribution panel. No utility connection.
Breaker and SPD ratings shown are sized at 125% of calculated current, per PEC continuous-duty practice β verify against manufacturer datasheets before installation.
01Load Analysis
List every appliance the off-grid system must run daily.
| Load | Qty | Watts | Hrs/day | Type | Daily Wh |
|---|
03Inverter Sizing (Surge)
Motor loads (fans, fridge, aircon, pumps) draw 2β3Γ their rated watts on start-up.
05Charge Controller
02PV Panel Sizing
Panel Rating (W)04Battery Bank
Battery ChemistryThis calculator reproduces the standard load-analysis β panel β inverter β battery β charge-controller sizing sequence taught in TESDA's Photovoltaic Systems Design and Installation curriculum, for preliminary estimation and training purposes only. It is not a substitute for a licensed engineer's system design, permit drawings, or manufacturer datasheet verification.